Project Timeline and Conceptual Cost

Study Schedule

Project Kickoff June 11, 2018
Neighborhood Survey Active through June 21, 2018
Stakeholder Meetings November 27, 2018
Implementation of Interim Bridge Repai April 8 through April 19, 2019
Submittal of 90% Construction Plans to FDOT June 14, 2019
Public Hearing September 10, 2019
Finalize PD&E Documents Fall 2019
PD&E Approval Fall 2019

Project Duration

Final Design Fall 2018 to Winter 2020
Bidding Phase Winter 2020 through Summer 2020
Construction Phase Fall 2020 through Spring 2023

Conceptual Project Cost

Planning & Design $ 1,052,393
Permitting $ 56,063
Construction $ 8,864,016
Construction Engineering Inspection $ 1,329,602
ESTIMATED TOTAL $ 11,302,074