Project Timeline and Conceptual Cost

Project Schedule

Project Kickoff / Public Meeting / Begin PD&E Study June 11, 2018
Neighborhood Survey Closed June 21, 2018
Stakeholder Meeting November 27, 2018
Implementation of Interim Bridge Repair April 8 through April 19, 2019
Submittal of 90% Plans to FDOT / Begin 100% Design June 14, 2019
Public Hearing September 10, 2019
Submittal of 100% Plans to FDOT / Begin Final Design October 22, 2019
Finalize PD&E Documents Spring 2020
FDOT Approval of PD&E Study (acceptance of design concept) May 4, 2020
First Submittal of Final Construction Plans to FDOT for approval January 10, 2020
Second Submittal of Final Construction Plans to FDOT for approval March 3, 2020
Third Submittal of Final Construction Plans to FDOT for approval April 10, 2020
Fourth Submittal of Final Construction Plans to FDOT for approval May 21, 2020
Fifth Submittal of Final Construction Plans to FDOT for approval July 6, 2020
Sixth Submittal of Final Construction Plans to FDOT for approval July 15, 2020
Authorization for Construction received July 29, 2020
Advertise Construction Documents for Bid August 5, 2020
Advertisement closes. Bids received September 24, 2020
Bids opened September 24, 2020
City Council Approves Construction Contract Award December 3, 2020

Project Duration

Study, Final Design and Construction Plans Summer 2018 to Summer 2020
Bidding Phase (after final approval from FDOT) Late Summer 2020
Phase 1 Completion Summer 2022
Phase 2 Completion Winter 2022/2023
Final Completion Fall 2023

Conceptual Project Cost

Planning, Permitting, & Design
  Bridge Replacement $ 1,255,000
  Utility Adjustment $ 75,766
Construction, Inspection, & Testing
  Bridge Replacement $ 12,609,217
  Utility Adjustment $ 993,236
Contingency $ 500,000
Bridge Replacement Total $ 14,364,217
Utility Adjustment Total $ 1,069,002
TOTAL COST $ 15,433,219