Project Timeline and Conceptual Cost

Project Timeline

Consultant Selection January 22, 2018
Project planning meeting with neighborhood association presidents February 13, 2018
Interim Improvements – Approval March 15, 2018
Interim Improvement Design – Notice to Proceed March 26, 2018
Neighborhood Survey #1 Active through June 18, 2018
Traffic Pattern Shift Completed June 7, 2018
Engineering Services (Bridge Design Report) Approval June 7, 2018
Public Meeting No. 1 – Project Kickoff June 11, 2018
Final Design Contract Approval October 4, 2018
Public Meeting No. 2 – Alternatives Workshop November 27, 2018
Council Approval of Interim Bridge Repair February 7, 2019
Typical Section Package Submitted to FDOT February 22, 2019
Submittal of 60% Construction Plans to FDOT March 4, 2019
Army Permit Pre-Application Meeting March 21, 2019
Implementation of Interim Bridge Repair April 8 through April 19, 2019

Looking Ahead

Submittal of 90% Construction Plans to FDOT June 17, 2019
Public Hearing Summer 2019

Project Duration

Final Design 18-24 months
Bidding Phase 3-6 months
Construction Phase 18-24 months

Conceptual Project Cost

Design $ 790,533.00
Permitting $ 50,000.00
Construction $ 8,000,000.00
Construction Engineering Inspection $ 800,000.00
ESTIMATED TOTAL $ 9,640,533.00