Project Schedule

Consultant Selection January 22, 2018
Project planning meeting with neighborhood association presidents February 13, 2018
Interim Improvements – Approval March 15, 2018
Interim Improvement Design – Notice to Proceed March 26, 2018
Neighborhood Survey #1 Active through June 18, 2018
Traffic Pattern Shift Completed June 7, 2018
Engineering Services (Bridge Design Report) Approval June 7, 2018
Public Meeting No. 1 – Project Kickoff June 11, 2018
Public Meeting No. 2 – Alternatives Workshop Fall 2018

Project Duration

Final Design 18-24 months
Bidding Phase 3-6 months
Construction Phase 18-24 months

Conceptual Project Cost

Design $ 790,533.00
Permitting $ 50,000.00
Construction $ 6,324,266.00
Construction Engineering Inspection $ 632,427.00
ESTIMATED TOTAL $ 7,797,226.00